COMPLETED CONSTRUCTION WORKS AND ORDERS, BUSINESS ENTITIES EMPLOYING 20 OR MORE PERSONS, FIRST QUARTER OF 2023

 

The value of new orders:

- increased by 24.0% in the first quarter of 2023, as compared to the same period of 2022.

 

The value of construction works done with own workers:

- increased by 25.6% in the first quarter of 2023, as compared to the same period of 2022.

1 INDICES OF CONSTRUCTION WORKS ON TERRITORY OF REPUBLIC OF CROATIA

     Indices
I – III 2023
X – XII 2022
I – III 2023
I – III 2022
I – III 2023
Ø 2022
Value of new orders 98,9 124,0 106,9
Value of construction works done with own workers 93,9 125,6 104,7

2 NEW ORDERS OF CONSTRUCTION WORKS ON TERRITORY OF REPUBLIC OF CROATIA

                                                                                                                  Thousand euro

    Value of new orders Value of new orders, by types of constructions
On buildings On civil engineering works
I – III 2023 1 171 127 687 668 483 459

3 VALUE OF CONSTRUCTION WORKS DONE AND BUILDING MATERIAL, COMPLETE UNITS AND STRUCTURES AND PROPULSION MATERIAL USED

                                                                                                                                          Thousand euro

    Value of construction works done Value of building material, complete units and structures and propulsion material used
Total Works done with own workers Works done with sub-contractors
I – III 2023 1 198 597 854 754 343 843 234 963

4 VALUE OF CONSTRUCTION WORKS DONE WITH OWN WORKERS, BY TYPES OF CONSTRUCTIONS AND WORKS

    Total, thousand euro Composition of value of construction works done, by types of works, %
Total New constructions Other works1)
I – III 2023         
Total 854 754 100,0 66,5 33,5
On buildings 483 219 56,5 42,9 13,6
On civil engineering works 371 535 43,5 23,6 19,9

1) Reconstructions, maintenance and repair works of existing buildings.

G-1 VALUE OF CONSTRUCTION WORKS DONE WITH OWN WORKERS, BY TYPES OF CONSTRUCTIONS AND WORKS, FIRST QUARTER OF 2023

G-2 COMPOSITION OF VALUE OF CONSTRUCTION WORKS DONE WITH OWN WORKERS, BY TYPES OF CONSTRUCTIONS, FIRST QUARTER OF 2023

 

NOTES ON METHODOLOGY

Sources and methods of data collection

Presented data on construction were collected through reporting method by using the Monthly Report on Construction (GRAĐ-21/M form) and the Quarterly Report on Construction (GRAĐ-21/3M form).

Coverage and comparability

The Monthly and the Quarterly Report on construction are collected from business entities (legal entities and tradesmen) and parts thereof employing 20 or more persons classified according to the NKD 2007 (NN, No. 58/07) into section F Construction in the Statistical Business Register.

Data refer to all construction works (new constructions and reconstructions, maintenance and repair works on existing constructions) done on the territory of the Republic of Croatia.

Constructions and works are classified according to the Classification of Types of Constructions.

Definitions

The value of construction works is presented in current prices and includes works actually done during the reporting period, irrespective of whether they are paid for or not.

The value of construction works done includes the value of work, building material, complete units and structures, propulsion material and electricity, expenses of construction machinery usage and equipment and other expenses related to the work in question.

The value of construction works done excludes value added tax, purchase costs of the land, project costs, surveying of land and supervising of services.

The value of new orders is the total value of the contracts made in a reference month with ordering parties. An order is considered to be made on the day when a contract is signed between the ordering party and the contractor.

New orders also include works done by a constructor on own account and for sale (e.g. business premises and dwellings). Referring to constructions on own account and for sale, it is assumed that the order is placed on the day when works have actually started and that the presumed value of works is included.

More detailed notes on methodology of these surveys are published on the web site of the Croatian Bureau of Statistics.

Abbreviations        
           
NKD 2007 National Classification of Activities, 2007 version
NN   Narodne novine, official gazette of the Republic of Croatia
             

 

Published by the Croatian Bureau of Statistics, Zagreb, Ilica 3, P. O. B. 80
Phone: (+385 1) 48 06 111
Press corner: press@dzs.hr

Persons responsible:
Milenka Primorac Čačić, Director of Business Statistics Directorate
Lidija Brković, Director General

Prepared by:
Srećko Palej and Mirjana Mikulić

USERS ARE KINDLY REQUESTED TO STATE THE SOURCE.

Customer Relations and Data Protection Department

Information and user requests
Phone: (+385 1) 48 06 138, 48 06 154
E-mail: stat.info@dzs.hr

Subscription
Phone: (+385 1) 48 06 115
E-mail: prodaja@dzs.hr

Postavke pristupačnosti